BOE Chengdu In-vehicle Display Base
The project was declared as a whole in September 2021, the EIA was conducted in December 2021, and the construction period is from 2021 to 2022. The construction period will be from 2021 to 2022. The first phase of the project will be completed and accepted in February 2023, the second phase will start construction in September 2023, and the acceptance will be completed in September 2024. After the project is put into operation, it will become BOE's largest centralized production base for in-vehicle display products, which can centralize the management of resources, build a large-scale module manufacturing base, reduce the cost, improve the quality, and perfect BOE's in-vehicle industrial layout.