Zhangjiagang Gangcheng Intelligent Intelligent Manufacturing Big Data Industrial Park
With a total construction area of about 280,000 square meters, the industrial park plans to build 11 data centers, 1 special substation and 1 operation and maintenance center, with a planned computing power capacity of more than 500MW and 22,627 cabinets after commissioning. It adopts wind-liquid homogenous dual cooling source air conditioning, with 85% liquid cooling, PUE no higher than 1.2, and more than 80% green power supply, and 100% green power supply will be realized by 2030.